Stearns County Road 75 Bridge Remains Under Construction
WAITE PARK (WJON News) -- Work continues on the Stearns County Road 75 Bridge over the Sauk River.
Stearns County Engineer Jodi Teich says they are paving the concrete roadway on the west side on Friday and will pave the turn lane on Saturday.
The bridge deck has already been poured and is in the mandatory 28-day window to cure.
Teich says next week crews will finish the roadway paving on the east side of the bridge and pour concrete for the curb and the median. Crews will also be putting down gravel on the shoulders next week ahead of asphalt paving on those shoulders starting the week of June 17th.
Teich says guardrail and striping work is scheduled to take place on Thursday, June 20th with the contractual completion date the following day on June 21st.
Teich says there will be some intermittent lane closures once the bridge opens. Crews need to close the temporary median crossing that allowed access to Opie's Gold and Modern Barnyard and complete the bridge joint work.
LOOK: Route 66’s quirkiest and most wonderful attractions state by state
Gallery Credit: Kery Wiginton
From coast to coast: The 20 best regional fast-food chains to try
Gallery Credit: Kiersten Hickman
LOOK: Explore the iconic buildings from every state
Gallery Credit: Aine Givens
More From 103.7 The Loon




![This Central MN Town Still Has a Band [GALLERY]](http://townsquare.media/site/67/files/2025/12/attachment-meire-grove-sign-1.jpg?w=980&q=75)
![This Central MN Small Town Has a Winery and Community Center [GALLERY]](http://townsquare.media/site/67/files/2025/09/attachment-kingston-fishing-in-the-river.jpg?w=980&q=75)